D9001 - 1965

D9001 (1964).....D9001 (1966)

January

Click for current timetable

1 -  
2 -  
s3 -  
4 -  
5 -  
6 -  
7 -  
8 -  
9 - 1N03 07:45 King's Cross - Leeds, "The West Riding".
1E10 11:34 Harrogate - King's Cross.
1A52 17:05 King's Cross - Newcastle.
s10 -  
11 -  
12 -  
13 -  
14 - 1A39 09:30 Glasgow Queen St. - King's Cross.
15 -  
16 -  
s17 -  
18 -  
19 -  
20 -  
21 -  
22 -  
23 -  
s24 -  
25 -  
26 -  
27 -  
28 -  
29 -  
30 -  
s31 -  

February

Click for current timetable

1 -  
2 -  
3 -  
4 -  
5 -  
6 -  
s7 -  
8 -  
9 -  
10 -  
11 -  
12 -  
13 -  
s14 -  
15 -  
16 -  
17 -  
18 -  
19 -  
20 - 1N06 09:20 King's Cross - Bradford.
1E15 17:00 Bradford - King's Cross.
s21 -  
22 -  
23 -  
24 -  
25 -  
26 -  
27 -  
s28 -  

March

Click for current timetable

1 - 1A30 14:00 King's Cross - Edinburgh, "The Heart of Midlothian".
2 - 1N10 10:20 King's Cross - Bradford.
3 - 1A28 13:00 King's Cross - Newcastle, "The Northumbrian".
4 - 1N03 07:45 King's Cross - Leeds, "The West Riding".
1E10 11:34 Harrogate - King's Cross.
1N24 17:37 King's Cross - Harrogate, "The Yorkshire Pullman"
5 -  
6 -  
s7 - 1A31 11:00 Newcastle - King's Cross.
8 -  
9 -  
10 -  
11 -  
12 -  
13 -  
s14 -  
15 -  
16 -  
17 -  
18 -  
19 -  
20 - To Doncaster Works - Unclassified repair.
No shopping proposal - boiler 1491/J2947 had a replacement burner motor fitted.
s21 - Doncaster Works.
22 - Released from Doncaster Works.
23 -  
24 -  
25 - To Doncaster Works - General repair.
No shopping proposal - power units No.1 449 & No.2 453 were given six-monthly repairs, bogies No.1 1041
was replaced by 1001 & No.2 1042 was replaced by 1050 and boiler 1497/J2947 replaced by 1486/J2942. The
body was given a General repair that also involved renewing No.1 end boiler water tank
.
26 - Doncaster Works.
27 - Doncaster Works.
s28 - Doncaster Works.
29 - Doncaster Works.
30 - Doncaster Works.
31 - Doncaster Works.

April

Click for current timetable

1 - Doncaster Works.
2 - Doncaster Works.
3 - Doncaster Works.
s4 - Released from Doncaster Works.
5 -  
6 -  
7 -  
8 -  
9 -  
10 -  
s11 -  
12 -  
13 -  
14 -  
15 - 1A30 14:00 King's Cross - Edinburgh, "The Heart Of Midlothian" (engine failure Welwyn - D5062 assist fwd).
16 - 0B01 (with D9012 - noted Great Paxton 19:25).
17 - 1A30 14:00 King's Cross - Edinburgh, "The Heart of Midlothian".
s18 - Haymarket TMD.
1A35 11:00 Edinburgh - King's Cross.
19 - 1A11.
20 -
21 -
22 -  
23 -  
24 -  
s25 -  
26 -  
27 -  
28 -  
29 -  
30 -  

May

Click for current timetable

1 -  
s2 -  
3 -  
4 -  
5 -  
6 -  
7 -  
8 - 1A35 10:00 Edinburgh - King's Cross, "The Flying Scotsman"
s9 - 1xxx (up additional). 
10 -  
11 -  
12 -  
13 -  
14 -  
15 -  
s16 -  
17 -  
18 -  
19 -  
20 -  
21 -  
22 -  
s23 -  
24 -  
25 -  
26 -  
27 -  
28 -  
29 -  
s30 -  
31 -  

June

Click for current timetable

1 -  
2 -  
3 -  
4 -  
5 - Up goods (noted Bathley Lane 17:15).
s6 -  
7 -  
8 -  
9 -  
10 -  
11 - 1A47 13:30 Edinburgh - King's Cross, "The Heart of Midlothian".
12 - 1E02 07:00 Bradford - King's Cross, "The West Riding".
1A30 14:00 King's Cross - Edinburgh, "The Heart of Midlothian".
s13 -  
14 - New timetable period.
15 -  
16 -  
17 -  
18 -  
19 - 1A42 15:00 King's Cross - Newcastle.
s20 -  
21 -  
22 -  
23 -  
24 -  
25 -  
26 -  
s27 -  
28 -  
29 -  
30 -  

July

Click for current timetable.

1 -  
2 -  
3 - 1A47 13:30 Edinburgh - King's Cross, "The Heart of Midlothian".
s4 -  
5 -  
6 -  
7 -  
8 - To Doncaster Works - Unclassified repair.
No.1 power unit 449 cylinder liner seal defective - 449 replaced by 422.
9 - Doncaster Works.
10 - Released from Doncaster Works.
s11 -  
12 -  
13 -  
14 -  
15 -  
16 -  
17 -  
s18 -  
19 -  
20 -  
21 - To Doncaster Works - Unclassified repair.
Boiler 1486/J2942 wiring burnt, 'NUWAY' parts to renew and leaking boiler tube - the 'NUWAY' burner was
repaired and the leaking boiler tube was re-welded
.
22 - Released from Doncaster Works.
23 -  
24 - 1N03 07:45 King's Cross - Leeds, "The West Riding".
1E10 11:40 Harrogate - King's Cross, from Leeds.
1A54 18:05 King's Cross - Newcastle, "The North Eastern".
Gateshead TMD.
s25 - Gateshead TMD.
1A43 13:30 Newcastle - King's Cross (via Murton and Haswell).
26 -  
27 -  
28 -  
29 -  
30 -  
31 -  

August

Click for current timetable.

s1 -  
2 -  
3 -  
4 -  
5 -  
6 -  
7 -  
s8 -  
9 -  
10 -  
11 -  
12 -  
13 -  
14 - 1A12 09:00 King's Cross - Newcastle.
s15 -  
16 - 1A66 20:20 King's Cross - Edinburgh.
17 -  
18 -  
19 -  
20 - 1B15 18:25 Doncaster - King's Cross.
21 - 1A47 13:30 Edinburgh - King's Cross, "The Heart of Midlothian".
s22 -  
23 - 1N03 07:45 King's Cross - Leeds, "The West Riding".
1E10 11:40 Harrogate - King's Cross, from Leeds.
24 -  
25 -  
26 -  
27 -  
28 - 1A03 07:50 Newcastle - King's Cross, "The North Eastern".
1A42 15:00 King's Cross - Newcastle.
s29 -  
30 -  
31 -  

September

Click for current timetable.

1 -  
2 - 1A30 14:00 King's Cross - Edinburgh, "The Heart of Midlothian".
3 -  
4 -  
s5 -  
6 -  
7 -  
8 -  
9 -  
10 -  
11 -  
s12 -  
13 -  
14 -  
15 -  
16 -  
17 -  
18 -  
s19 - To Doncaster Works - Unclassified repair.
Fuel tank and boiler water tank damaged - No.1 left hand fuel tank was repaired, bogies No.1 1001 replaced
by 9000-23 & No.2 1050 replaced by 9000-24. Boiler 1486/J2942 had its burner motor changed. All traction
motors were replaced and breakgear was overhauled
.
20 - Doncaster Works.
21 - Doncaster Works.
22 - Doncaster Works.
23 - Released from Doncaster Works.
24 -  
25 -  
s26 -  
27 -  
28 -  
29 -  
30 -  

October

Click for current timetable

1 -  
2 -  
s3 -  
4 -  
5 -  
6 -  
7 -  
8 -  
9 -  
s10 - 1A43 13:30 Newcastle - King's Cross.
11 -  
12 -  
13 -  
14 -  
15 -  
16 -  
s17 -  
18 -  
19 -  
20 -  
21 -  
22 -  
23 - 1A03 07:50 Newcastle - King's Cross, The North Eastern".
1A30 14:00 King's Cross - Edinburgh, "The Heart of Midlothian".
s24 -  
25 -  
26 -  
27 - To Doncaster Works - Light repair.
No shopping proposal - No.2 power unit 453 replaced by 427, bogies No.1 9000-23 & No.2 9000-24 were
given a Light repair and boiler 1486/J2942 was acid descaled. The following modifications were carried out:-
protection bars for EP valves; Fire alarm bell gong
.
28 - Doncaster Works.
29 - Doncaster Works.
30 - Doncaster Works.
s31 - Doncaster Works.

November

Click for current timetable

1 - Doncaster Works.
2 - Released from Doncaster Works.
3 -  
4 -  
5 -  
6 - 1N13 11:40 King's Cross - Harrogate, "The White Rose".
s7 -  
8 -  
9 -  
10 -  
11 -  
12 -  
13 -  
s14 -  
15 - 1A12 09:00 King's Cross - Newcastle, to York (engine failure - D272 forward).
16 -  
17 -  
18 -  
19 -  
20 -  
s21 -  
22 - 1Axx Edinburgh - King's Cross (sleeper arrive 23/11).
23 -  
24 -  
25 -  
26 -  
27 -  
s28 -  
29 -  
30 -  

December

Click for current timetable

1 -  
2 -  
3 -  
4 -  
s5 -  
6 -  
7 -  
8 -  
9 -  
10 -  
11 -  
s12 -  
13 -  
14 -  
15 -  
16 -  
17 -  
18 -  
s19 -  
20 -  
21 -  
22 -  
23 -  
24 -  
25 -  
s26 -  
27 -  
28 -  
29 -  
30 - To Doncaster Works - Unclassified repair.
Boiler 1486/J2942 split tubes - 1486/J2942 replaced by 5090/J3241.
31 - Doncaster Works.

D9001 (1964).....D9001 (1966)